Leading up to and throughout the course of the Mars Area Middle School Renovation Project, Mars Area School District will post information about the project on this page as soon as it becomes available.

Progress Reports 
 
The following are Monthly Progress Reports on the Mars Area Middle School Renovation Project, as provided to Mars Area School District by Thomas & Williamson Project Management. The latest reports will be posted as they become available.
Air Quality Testing (posted 09.09.19)
 

The following reports list qtrak (temperature, carbon dioxide, relative humidity and carbon monoxide) and dust data at Mars Area Middle School. The numbers on the dust trak is the average, according to Michael Kopar of Intertek-PSI. The highest amount recorded was  0.033 mg/m3 in the hallway outside Room 185. Levels below 0.050 mg/m3 are normal. All other levels are normal — carbon dioxide (less than 1,100 ppm), relative humidity (less than 65 percent), Carbon Monoxide (less than 9). 

The following are the VOC (volatile organic compound) results for air quality testing conducted at Mars Area Middle School:
Project Updates

Middle School Renovations Continuing Ahead of Schedule

Work on the Mars Area Middle School Renovation Project is continuing ahead of schedule, according to John Hays of Thomas & Williamson Project Management.

“We are on time. In fact, (Phase 4) is ahead of schedule by about two weeks,” said Hays, noting that the project phase includes renovations to the remaining classrooms in the school’s eighth grade wing. “The goal is to get it done and move on to Phase 5.”

Phase 5 will include renovations to the “switch” classrooms, to which teachers were temporarily moved while their classrooms were updated, said Hays. The entirety of the project is expected to be completed in December, in accordance with the planned construction schedule.

The overall project includes renovations to all classrooms; the installation of a new floor, new lighting and air conditioning in the gymnasium; the raising of the floor in The Commons (cafeteria); and the expansion of the kitchen/cafeteria serving area and the school’s LGI (Large Group Instruction) Room. New mechanical equipment, flooring and lighting was installed throughout the building and all areas are being painted.

The Guidance/Nurse’s Office was moved to the front of the building near the Main Office. And, the school’s Technology Education classroom were expanded into existing space; the Art and Family & Consumer Science classrooms were relocated and enlarged; and classrooms were dedicated for a “Maker” Lab and Robotics Lab.

All remaining construction activity has been planned to avoid disruption to the instructional day with the majority of work being completed after school hours.

For more information, call (724) 625-1518.

Presentations (updated 02.05.19)
 
The following are all available presentations addressing the Mars Area Middle School Renovation Project:  


Questions/Comments

Questions or comments regarding the Mars Area Middle School Renovation Project may be submitted to Mars Area School Board via e-mail at [email protected] or at any public Board meeting.